Design Optimization of Utility System of Angren Rubber Factory |
Received:October 15, 2020 Revised:October 15, 2020 |
DOI:10.12136/j.issn.1000-890X.2021.05.0374 |
Key Words: rubber factory;utility system;boiler room;air pressure station;power station;water pumping station;refrigeration station;transformer and distribution substation |
Author Name | Affiliation | E-mail | PEI Hongbing* | Beijing Rubber Industry Research Design Institute Co.Ltd | 769252800@qq.com | AI Yongan | Beijing Rubber Industry Research Design Institute Co.Ltd | | YAN Xiaoxing | Beijing Rubber Industry Research Design Institute Co.Ltd | | ZHANG Ke | Beijing Rubber Industry Research Design Institute Co.Ltd | |
|
Hits: 1127 |
Download times: 600 |
Abstract: |
Uzbekistan Angren Rubber Factory construction is a Belt and Road Initiative project. This
paper introduced the design optimization of the utility system of this factory. In order to further control
costs,facilitate implementation,and make equipment operation and maintenance more convenient,some
optimization schemes were put forward,such as addition of water seals to the overflow pipe of deaerator in
the boiler room,taking partition use of condensation tanks in the boiler room,adding a heat exchanger at the
inlet of hot vacuum tank in the power station,using of the existing pumps of the refrigeration system as the
backup for each other with the same function,adding supplementary water pipelines to the water reuse pool
in the sewage treatment,and moving the area A transformer and distribution substation close to the power
load center and the main substation. These optimization schemes were proved to be effective in practice,and
had certain reference significance for the design of utility system of similar project |