闫小星,艾永安,盖 强.密炼机的安装和调试[J].轮胎工业,2023,43(1):0046-0050 |
 二维码(扫一下试试看!) |
密炼机的安装和调试 |
Installation and Commissioning of Internal Mixer |
投稿时间:2021-12-16 修订日期:2021-12-16 |
DOI:10.12135/j.issn.1006-8171.2023.01.0046 |
中文关键词: 密炼机 安装 调试 点检 记录 |
英文关键词: internal mixer installation commissioning spot check record |
基金项目: |
中图分类号: |
|
摘要点击次数: 1332 |
全文下载次数: 975 |
中文摘要: |
介绍密炼机的安装和调试,对各分项工程主要流程和工序提出明确要求。密炼机安装前需要进行技术资料和现场施工条件准备。密炼机安装过程如下:确定安装计划和安装工序,按作业工序进行安装,注意安装垫铁尺寸和垫铁安放方式、设备找正、正确使用地脚螺栓及设备找水平。密炼机调试顺序如下:高压润滑泵启动、减速机润滑系统启动、液压站系统启动、温控系统启功和主电动机启动,调试中对现场检查项目进行肉眼或仪器检查,详细填写检查记录表,确保密炼机试运转达到投产条件。有效安装和调试密炼机可提高工作质量和效率,节约时间和成本。 |
英文摘要: |
The installation and commissioning of internal mixer were introduced,and clear requirements for the main processes and procedures of each sub project were put forward.Before installation of internal mixer,technical data and site construction conditions should be prepared.The installation process of internal mixer was as follows:determine the installation plan and installation process,install according to the operation process,pay attention to the installation sizing block size and sizing block placement method, equipment alignment,correctly use anchor bolts and equipment leveling.The commissioning sequence of the internal mixer was as follows:start the high-pressure lubricating pump,start the lubricating system of the reducer,start the hydraulic station system,start the temperature control system and start the main motor.During the commissioning,visual or instrument inspection on the on-site inspection items were carried out,and filled in the inspection record in detail to ensure that the internal mixer commissioning to meet the production conditions.Effective installation and commissioning of internal mixer could improve work quality and efficiency,and save time and cost. |
|